Haiti - Les Cayes Airport : Modernization work nearing completion - HaitiLibre.com : Haiti news 7/7
 New revised electoral calendar (Oct. 28, 2026)





Construction monitoring of the mini-power grid in Marfranc

iciHaiti - National D1 Championship : Victory for Violette AC [1-0] – Standings and Schedule for Matchday 4

iciHaiti - Education : Rehabilitation of the Lycée Marie Jeanne

iciHaiti - DINEPA : Open Day dedicated to sanitation

Cap-Haitien : Sunrise Airways, first flight of the new direct route to New York


more news


Haiti - News : Zapping...

Haiti - Electoral statistics : Nearly 1 million registered voters

Haiti - Education: Minister Déméro concerned by poor performance on the 9th AF official examinations

Haiti - South : An ILO project creates more than 8,600 workdays

Haiti - 2026 U-17 World Cup (Qatar) : Haiti saves its honor but falls [3-1] against France


more news


Haiti - Les Cayes Airport : Modernization work nearing completion


Haiti - Les Cayes Airport : Modernization work nearing completion

The renovation work at Antoine Simon International Airport, launched in September, was 80% complete by mid-December, with an initial delivery date of December 31, 2025.

Compliance with international standards (TSA and ICAO) : These interventions, while temporary pending the launch of the future master plan, aim for immediate and secure operation. A crucial milestone has already been reached: in early December, the airport received approval from the Transportation Security Administration (TSA), officially opening the way for direct flights between the United States and Les Cayes. https://www.icihaiti.com/en/news-46347-icihaiti-les-cayes-good-news-for-antoine-simon-international-airport.html

A task force from the National Airport Authority (AAN) is currently deployed on-site to ensure strict compliance with standards. It is composed of :

  • The International Civil Aviation Organization (ICAO);

  • The Federal Aviation Administration (FAA);

  • The National Civil Aviation Office (OFNAC).

Main terminal improvements :

The project, carried out by the Haitian firm SD Construction S.A. under the supervision of BETA Consulting Engineers, transforms the passenger experience:

  • Improved flow :

    Repositioning of check-in counters and the Security Checkpoint (SCR);

  • Sovereign Services:

    Creation of dedicated areas for immigration (departure/arrival) and customs;

  • Comfort :

    Construction of an international departure lounge, a VIP lounge, and full terminal air conditioning;

  • Logistics :

    New baggage handling area and relocation of Sunrise Airways' ticketing/cargo services.

Security and Technical Infrastructure :

In addition to the terminal, perimeter security work is underway :

  • Installation of a temporary lighting system;

  • Construction of a Road Access and Screening Post (PARIF);

  • Imminent commissioning of technical rooms for IT and video surveillance.

HL/HaitiLibre